Weiss Lane Transmission Main
CobbFendley performed design, bid, and construction phase services for 6,200 linear feet of 24-inch waterline along Weiss Lane, 2,600 linear feet of 12-inch waterline to access a new Pflugerville ISD High School, and 5,000 linear feet of 16-inch waterline relocation for Manville WSC. Phase 1 of this project was fast-tracked to accommodate construction of the new high school. Design and construction of 1,000 linear feet of 24-inch and 2,600 linear feet of 12-inch waterline was accomplished in seven months to keep the school construction moving forward.