Cornudas Pipeline Project
The El Paso Water Utilities – Public Service Board (EPWater) selected CobbFendley to provide services required for the acquisition of right-of-way (easements) for an 81-mile pipeline from east El Paso in El Paso County to the Hudspeth/Culberson County line. The pipeline, once constructed, will carry water from Dell City to Clint, Texas. Our efforts included land surveying and acquisition of impacted parcels for three segments of water pipeline, GIS mapping, and preparation of a due diligence report for 98 previously acquired easements, as well as project administration Our team identified and established ownership and right of entry for 272 individual parcels impacted by the proposed pipeline, and created and maintained a database detailing the attributes of each individual parcel including ownership, deed history, legal description, parent tract identification, title research, and tax information.